2024欧洲杯下注平台 > Project construction

  On April 13, with the roar of pavers, bulldozers, road rollers and other mechanical equipment, the G3 Tongling Yangtze River Highway Railway Bridge North Approach Bridge undertaken by Comprehensive new road materials Company was successfully completed。

  The cement-stabilized gravel base paving section is K0+370-K0+875, with a length of about 505 meters, a width of 22 meters, and a compacted thickness of 20 centimeters.5% cement stabilized gravel, the total amount of 5049.4吨。To ensure the smooth smooth paving of highway water stability,The production department and materials Department of the company closely coordinate the key production factors such as machinery and equipment, materials and materials,Several special construction work meetings were held,Organize machinery approach in an orderly manner,Strengthen safety technology disclosure for management personnel and labor cooperation teams,Strictly control the mixing, transportation, spreading, rolling, testing, maintenance and other processes of the water stabilized mixture,Control from quality and safety,Ensure water stability laying connection orderly, efficient operation,It lays a solid foundation for the smooth construction of the subsequent asphalt pavement of the Baotong section of G3 Railway bridge。